Activities:
|
- Attended pre-construction meeting for implementation
of Oak Street Pedway Corrective Action Plan
with Contractor, Project Engineer, St. Johns
River Water Management District (absent), Brevard County Utilities and
City of Melbourne Water Department (absent).
- Attended meeting for residents with property
adjacent to work areas of the Oak Street Pedway
Corrective Action Plan Project.
Construction
activities are scheduled to begin Monday, July 16th and conclude
December, 2007. Initial activities will start at the intersection of First
Avenue & Oak Street.
- Reviewed departmental budget requests for the
development of the FY 2008 budget. Budget to be transmitted to Town
Commission the week of July 23rd, with presentation to the
Town Commission the week of July 30th.
- Public Works staff completed repairs to
Avenue A dune crossover damaged by vehicle. Claim filed with owner seeking
reimbursement of costs.
|